Selection of UPS E-mail
Typical Things to Keep in Mind while selcting a UPS

When selecting an uninterruptible power system (UPS), maintenance and engineering managers must consider the following factors that can make or break the success of the system:

  1. Load size
    The size of the critical load determines the capacity of the initial installation. The UPS must have adequate capacity to reliably serve the critical load and additional loads, without immediate expansion. The excess capacity of a UPS will depend on the facility's plans for expansion of the supported load.

    In general, capacity should be 150-200 percent of the initial installed load. For small critical loads involving a single computer or a few racks, a single-phase desktop or rack-mounted UPS might be the optimal solution. For larger critical loads, such as data centers, freestanding three-phase modules generally are installed.

     
  2. System reliability
    System-reliability requirements will determine the configuration of the power system. Very high requirements will lead to a system with multiple UPS modules and multiple battery banks. The system also should have at least one redundant module so it can reliably serve the load if one module fails or undergoes maintenance.

    A single UPS module with a static bypass switch can serve loads with lower requirements to provide utility or generator power during periods when the module is down. The consequences of a power failure tend to dictate reliability needs. If an outage would result in lost revenue, the failure to meet contractual obligations, or lost customer goodwill, it is appropriate to install a redundant system.

     
  3. Battery run time
    The battery run time of a UPS is the length of time the UPS can reliably supply power to the critical load after input power has failed. Run time usually is defined as the length of time required for connected data-processing equipment to save data files and shut down in an orderly fashion, along with a margin of safety. Typical battery run time is 15 minutes.

    Batteries are heavy and can present a large dead load to a structure, so managers must make sure a structural engineer reviews the proposed installation to determine if modifications are necessary to support the load.

     
  4. Future expansion
    Requirements for future expansion affect UPS configuration and determine space requirements for future modules and battery banks. Depending on the timing of the expansion, it might be more economical to install a single module and add modules as needed, rather than installing a single, larger module.

    Managers who intend to install more capacity later should consider the electrical infrastructure required to support the maximum load, and they must carefully guard spaces allocated for expansion to ensure those spaces are not filled with other equipment.

     
  5. Budget constraints
    Budgetary constraints play a key role in determining the final UPS design. Often, a system that satisfies other considerations simply will be too expensive to implement, and some functionality or system reliability will have to be sacrificed to keep costs in line
For more information about how to select a UPS: Call 91-11-26567985,or 91-11-26527981  or Fax: +91-11-41040255  or email at This e-mail address is being protected from spambots. You need JavaScript enabled to view it
 